Sunday, June 30, 2013

Hooking up the electricity

The electricity was hooked up today after some discussions with the electrician, Atlas Tech Support, and some searching on the Web. Tech Support sent me their diagram which is similar to the Square D QO 230GFI model that I am using. Tech Support was again very prompt.

The steam shower was given a final sealing around the base with clear GE silicon.

The whole house surge protector and GFCI were tested and the steam shower powered on. The display was bright and clear. All functions operated, and the shower moved back into position. The steam generator filled the shower with steam and the default temperature of 104 F was quickly reached. A pair of Sioux Chief water hammer arresters will be added to the supply lines on Tuesday to reduce the noise of the water lines when the solenoid that supplies water to the generator opens and closes.

















Saturday, June 22, 2013

Finally back together

I should have finished all the painting, but I was to anxious to see how well the bed would fit in the room. I will just have to pull it away from the windows and carefully paint the trim. It will be nice to be back in my own bed after 3 weeks of sleeping in the guest room.


Friday, June 21, 2013

One...not quite done

Well the last day of construction was today. It was a valant effort, with the electrician staying until 6:30 and the contractor until 9:30, but things just didn't go smoothly as we had hoped. That is usually how things go, and the last little bit always seems to take a lot longer than planned.

To start, the shower was a bit difficult to level. That had a lot to do with the floors, as there is a drop to the center of the room throughout the whole house. It actually worked out ok though, as it will allow me to use a thick, soft and absorbent rug in front of the shower. The shower glass was assembled and sealed. That took about 3 hours. Some of the hardware was a little different than the directions, and some of the directions were just plan missing. The changes were actually better, so they must have made some improvements. It just took some thinking to figure out what to do with some of the parts. But we did get it together, and it looked nice.

The GFCI circuit was not as easy. The electrician is going to check with the factory to make sure that we fully understand it before applying the power. So no steam shower for a while until that is figured out. Better to be safe.

Still a lot to finish over the coming weeks. The baseboard needs to be painted, the venting for the exhaust fans needs completed. We also had some problems with the vanity. It did not come with any instructions, so once again we had to fumble through it. The chrome drain stem and the faucet lines were not long enough. We were able to get some extensions for the lines, but it was too late in the day to find the right stems. So the vanity is not yet usable. I opted to wait until we could get chrome rather than forge ahead with PVC pipe.

At least we know what it will look like now, and I can work on cleaning and painting.




















Thursday, June 20, 2013

Two..Almost Through

A morning of wall trim work and floor transitions. The 3 inch wide floor transition between the tile area and bedroom was joined by more of the hardwood flooring. The idea of doing either glass mosaic or some other material created too many different material transitions. Instead, we will frame the floor with some of the existing wood flooring that was left over from the previous floor installation. This will create a less dramatic change in flooring, and mend the two flooring types together. The bathroom window was framed and the toilet is ready to be installed tomorrow.

The Steam Shower was assembled and is ready for the final plumbing and electrical connections.

Wednesday, June 19, 2013

Three...The Calm before the Storm

There is no work scheduled for Wednesday. It is a day of rest for the paint, tile, and grout. Thursday the construction will be wrapped up, the floor transition will be completed, and the bathroom window will be trimmed out. The steam shower will be assembled and ready for Friday's electrical connection. The vanity should arrive either Thursday or Friday, as it is the last thing to be installed.

A couple more "additions" to the project has crept in. An RFFE20-BB Radial Flow Iron Reduction Cartridge replaced the first stage micron filter in the two-stage Big Blue whole house filtration system that was installed last year. The last time I changed the pleated filter, there wasn't much in it so it wasn't really necessary.

The first stage RFFE20-BB
filter cartridge is designed to provide an easy and effective method of reducing iron from water, which greatly improves the taste.  This cartridge will eliminate the orange and brown stains found in sinks, toilets, tubs, and the Steam Shower generator. It will also reduce the possibility of damage to pipes and the water heaters and reduces up to 3 ppm dissolved iron. It adds no harmful chemicals to the water, making it completely safe for drinking water applications.

The second stage CRFC20-BB
filter cartridge incorporates a 70-micron porous polypropylene outer shell and a spun polypropylene-wrapped core. The bed of granular activated carbon (GAC) between the outer shell and core creates a unique radial flow design which effectively removes chloramine, has a low pressure drop, and helps to reduce fines commonly seen in GAC-style cartridges. Fairfax Water uses two types of chlorine: free chlorine from April to June as part of their annual flushing program and chloramines the rest of the year, which is a chlorine and ammonia mixture. Don't want either of these in my drinking, cooking, or bathing water.

A whole house surge protector will be added to protect the electronics in the house. The electronics in the theater room, the  new appliances in the kitchen, and the computerized steam shower should all be protected now. After a lightening strike near my house last spring, I am not taking any chances.


Tuesday, June 18, 2013

Four.....Main area Painted

The contractor arrived bright and early today at 7 am. The main bathroom area was painted and some height adjustments made to the toilet stall door area to accommodate the unique accordion door. The tiles were buffed back to their original luster.

The main bedroom area paint is Valspar Blue Lagoon. A nice, relaxing blue-green.




The arrival of the vanity has been an ordeal. Although they typically carry this model in their warehouse, when I went to purchase it last week, they were out of stock. To further complicate matters, new stock was not expected until the end of the month. After further conversations with Home Design Outlet Center, we found one that could be shipped from their NJ warehouse. Unfortunately, I had to pay for additional shipping, but the alternative of waiting another week and trying to get the contractor back was not acceptable. The vanity should arrive at their warehouse by the end of today, and then I can schedule the home delivery.

When going through the Steam Shower boxes, I found some large brackets that were not described in the manual. I sent off an email to Ken at Atlas at noon, and within a few hours he had written back with an explanation. The brackets are something new that has been added to ensure that the shower rests firmly against the wall, but also provides the necessary clearance to prevent any wires, pipes, or other items from being pinched against the wall. It was a nice addition, and once again I was impressed with the quick response of Atlas tech support.










Monday, June 17, 2013

Five.....Paint and Grout

The ceiling was given two coats of fresh UltraWhite paint this morning. The first coat of paint was also applied to the new bathroom area. The color selected was Valspar Daydream Haze. It is from the cool white family of colors with a slightly muted light green/blue glass tint. It should blend nicely with the back-painted glass of the Steam Shower.



This color was also used in the toilet area and the small alcove near the entrance to the bedroom. I wanted to reflect as much light as I could into the main bedroom area since it will be a darker color. I also wanted to keep the area around the shower and vanity bright, and at a color temperature above the 3000K color of the overhead LED lights. The slight tint of green should increase the color temperature to something closer to natural daylight. The color definitely changes from green to blue to almost white depending on the angle and intensity of the light in the room.

 A second coat will be applied, and the first coat applied to the main bedroom area tomorrow.

The tiles were grouted at the end of today. The tiles are Florida Tile Magnificent Ivory from their Grandeur Natural Series.



"The Grandeur series is the newest HDP – High Definition Porcelain line by Florida Tile. Created with the newest digital printing technology, this Breccia Marble has been the staple floor and wall covering for centuries. From the civic buildings that lined the Palatine Hill and the palatial villas of Roman emperors to the modern steel and glass high-rises of our global cityscapes,"

I was able to sort through the boxes and pick the tiles I thought were the most pleasing for the area near the bedroom, and the ones that had a touch more brown for the area of the vanity so that it would blend more smoothly into the cabinetry. The grout was a light pewter gray, and it blended nicely with the tiles. Tomorrow morning the remaining light haze will be removed and the tiles buffed back to their original shine.












Friday, June 14, 2013

Final Week

With the walls all primed, the floors can now be secured and tile laid today. We are now in the final week of construction. I plan to pick the paint this weekend, and having the floor down will help me find a matching color.

The electrician has been scheduled for next Friday, and that should be the final day. It is going to be an interesting week to see how things finally come together.







Wednesday, June 12, 2013

Time to start on the floors

With the drywall nearly completed, the original plan was to paint. That plan was changed today in order to allow more time for the tile floor to cure before putting the vanity and steam shower in place. Tomorrow the final work will be completed on the drywall, and then the floors will be prepped. The floors will be screwed down and durarock installed.

Friday, the tiles arrive and installation will begin. This will give the tiles until Monday to cure. On Monday, the walls can be primed and painted. Fortunately, this gives me another weekend to finally pick the paint color. Since most of the walls will be covered by the mirror, or obstructed by the vanity and steam shower, the bedroom will show most of the color. That may change my hue selection to something more blue than green.

The tiles can be grouted on Tuesday, vanity is scheduled to arrive.  Wednesday they can be installed. That leaves Thursday and Friday to finish the electrical and hang the lighting and fans.

If we stick to plan, I will be very pleased. With a week to go, the finish-line is starting to come into sight.

Tuesday, June 11, 2013

Day 2 of Drywall

The contractor was anxious to get started on the fun part, and arrived at my house before 8 am this morning. Drywall is his specialty and he has a passion for it. He is very meticulous and wants the drywall to look perfect. The waterproof drywall was tacked up yesterday, and the room took on its final form. Although I didn't want to replace any of the ceiling drywall if possible, we may replace one sheet over top of the shower. There was already a lot of holes in the ceiling from the old light and fan, so it may be quicker and fewer joints if we just replace the entire piece.

Picked out the tile today.  It has a multi-colored marbled veins for the look that I wanted, but made of porcelain for the low maintenance care and cleaning that I needed.